Guidance > Piling Specification > Errata Piling Specification - Errata 2007Download a pdf version of this document There are errors in transcription in the first two print runs of ICE’s second edition of the Specification for Piling and Embedded Retaining Walls. These are shown in RED as below In Table B1.4 Standard installation tolerances (page 33)
In B1.14.1 Driving procedures and redrive checks (page 41) Line 10 “blows/25mm” should be “blows/250mm” In B1.14.3 Set (page 42) Last line “penetration of 250mm” should be “penetration of 25mm” Purchasers will have different updates on these errors dependent upon their purchase timing. It is intended that this note alerts all purchasers to the problem errors and that it can be referred to when clarification is needed for Specification discussions. |
Documents AvailableIntroduction of the ICE Piling Specification Tender Documents and Method of Invitation Measurement of Piling and Embedded Retaining Walls Cutting Down and Breaking Down Piles FPS Electronic Bearing Pile Schedule FPS Electronic Bearing Pile Schedule for use with Eurocodes See also guidance on this site under:Guidance > Working Platforms Guidance > Safety
ReferencesGround Forum Electronic Tendering Protocol for Geotechnical Works
|
|
||||||||||||||||||||